Strive to put into operation the 500kV transmission line, circuit 3, extending to the North by June 2024

In the afternoon of 8 July, the Ministry of Industry and Trade held an online conference with 9 provinces and some agencies and units on the situation of implementing the project of 500kV transmission line, circuit 3, extending to the North to ensure the progress of power supply.

 

 

 

 

 

 

 

Provincial leaders and delegates attended the conference at Thai Binh bridge point.

Comrade Nguyen Hong Dien, Member of the Party Central Committee, Minister of Industry and Trade chaired the conference.

At Thai Binh bridge point, the comrades: Nguyen Khac Than, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People’s Committee; Nguyen Quang Hung, Member of the Standing Committee of the Provincial Party Committee, Standing Vice Chairman of the Provincial People’s Committee and leaders of some related departments, sectors and units attended the conference.

The 500kV transmission line, circuit 3, extending to the North passes through 9 provinces including: Quang Binh, Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, and Hung Yen. This is a national key project, an urgent project directly directed by the Prime Minister and required to speed up the completion progress to ensure the power supply for the North.

At the conference, representatives of units and localities reported on the situation of preparation work for the project deployment such as alignment, planning, conversion of land use purposes and site clearance work, project construction option...

https://media.baothaibinh.com.vn/upload/news/7_2023/dchung_18024608072023.jpg

Comrade Nguyen Quang Hung, Member of the Standing Committee of the Provincial Party Committee, Standing Vice Chairman of the Provincial People’s Committee addressed at the conference.

On behalf of Thai Binh Provincial People’s Committee, addressing at the conference, Standing Vice Chairman of Provincial People’s Committee said: Located on circuit 3 extending to the North, Thai Binh has a 500kV transmission line from Nam Dinh 1 - Pho Noi Thermal Power Plant. According to the planning, the project will pass through the districts of Vu Thu, Dong Hung, Hung Ha and Quynh Phu with a total length of about 39km with 94 pole pits. Up to now, Thai Binh Provincial People’s Committee has document for comments on the project investment policy; the land area used for the project has been included in the provincial land use planning for the period of 2021 - 2030 and the land use plan of the province for the period of 2021 - 2025. Thai Binh will direct departments, sectors, units, localities to closely coordinate with Vietnam Electricity (EVN) and the project employer to deploy the site clearance, ensure security and order, and other tasks arising during the implementation and process of project operation management.

To ensure the project deployment progress under the direction of the Prime Minister, Thai Binh proposed to allow the province to actively adjust the land use plan in 2023; at the same time, requested the project employer to appoint a contact point to coordinate with the province in site clearance, especially the work of extracting measurements, extracting, and publicizing the project for the people to grasp thoroughly and facilitate the recovery, site clearance, site hand-over to serve the project in accordance with the progress.

Concluding the conference, Minister of Industry and Trade Nguyen Hong Dien emphasized: This is a key and urgent project, thus it is necessary to soon complete the investment. To do so, by the end of July 2023, EVN must review and complete the project documents to submit to the Government for approval. After the project and investment policy are approved, EVN and the employer must work with localities to deploy the project implementation steps in accordance with the regulations. The localities keep intact the alignment and update the planning of the province; convert the land use purpose; ensure the site clearance and resettlement. The agencies of the Ministry of Industry and Trade shorten the project appraisal time, strive to complete the investment of the entire project by June 2024 and put the 500kV transmission line, circuit 3, extending to the North into operation to meet the energy source to serve the socio-economic development of Northern provinces as well as the whole country.

 


Author: According to Baothaibinh.com.vn
The total score of the article is: 0 in 0 evaluate
Click to rate the article
Related listings
Bản đồ hành chính
Administrative map

Geographical location

Area: 1586.3 Km2

Population: 1.791.510 người

WEATHER IN ZONES
Statistical access
Today : 5
Yesterday : 20